Work continues to move along with the two pipe crews working on the project currently. With that we are in the middle of the major road closures portion of the project and so this entry into the blog is an update with the latest information on street closings related to the East Central Storm Water Project.
Expansion Blvd.
The section of road taken out on Expansion Blvd. by the Radio Tower site has been replaced and was opened back up to traffic last week.
The section of road taken out at the intersection of East 4th Street was poured back on Tuesday, August 27th and pending positive test results on Friday should be opened on Friday or Saturday morning.
Richland St.
A portion of Richland Street at the intersection of Ray Street was removed late last week and crews should be through the area and ready for pouring back that section yet this week. Curing time on the concrete will take us into next week before the road will re-open (hopefully around the middle of the week).
East 4th Street
Once they have reopened the section of Expansion Blvd. at the intersection with East 4th Street they will close down East 4th Street at the old railroad tracks area. This will require traffic to route around East 4th Street using Richland to Expansion and then into the Rose, Tulip, and Violet Lane areas. Based on the current schedule we would anticipate that East 4th Street will be closed down at the earliest on Friday, August 30th or for sure on Tuesday, September 3rd.
Rose Lane (East Cul-de-sac)
Work will begin next week on the installation of storm water piping in the Rose and Tulip Lane areas. For this work the cul-de-sacs on the east end of those streets will be torn out and replaced following the installation of storm drain pipe. Rose Lane will be the first of these streets to see construction. Emergency vehicle access will be maintained and a paving schedule has been developed which is available on the project web page. Residents affected by this closure are asked to keep vehicles off of the street during the construction process and until the road is paved back.
The best guess for work to begin on Rose Lane would be Wednesday (9.4) and Thursday (9.5).
Tulip Lane (East Cul-de-sac)
Work on this cul-de-sac area will follow the work on Rose Lane and should be about two (2) weeks behind that project's start.
In Addition -
The dirt crews are also back working on the remaining ponds and shaping ditches where the pipe crew has finished installing pipe. They will be hauling more dirt off the project site including hauling dirt to the City's spoil containment facility across from McKenna Drive.
The last time we had hauling to that area we had issues with dust and the contractor has been reminded that they need to keep the dust under control. The project inspector will also be keeping an eye on this as well.
Project Blog for the City of Storm Lake East Central Storm Water Project
Wednesday, August 28, 2013
Thursday, August 22, 2013
Project Keeps Rolling Forward
Things continue moving forward on the project front with construction aspects in the northern half of the project going full steam ahead.
The above picture is a junction area for intakes coming in from the various directions along East 4th Street and for me anyway it really is a symbol of all the various things occurring with this project including flood relief and cleaning of storm water all combining for relief and cleaner water. In order for everything to work it takes multiple angles and lots of dedicated people to make this project work, both now during construction but after construction is complete as well. We will need the help of residents to help keep trash and grass out of the storm water to help prevent the system from clogging up and debris from getting into the ponds and other treatment facilities.
On the construction side work continues with two crews working on the installation of piping.
The seeding contractor has ordered the plugs for the ponds at the golf course and should be back in Storm Lake after Labor Day to start planting those ponds.
Junction of several Storm Water Lines along East 4th Street. |
On the construction side work continues with two crews working on the installation of piping.
Pipe crew installs pipe along Richland Street |
Crews are now past Expansion Blvd at the intersection of East 4th Street and working west. The next big closure there will be the closing of East 4th Street. Expansion should be open at that point.
An additional closure will occur on Richland Street near the intersection with Ray Street. That closure could occur next week as well. Expansion Blvd should be open near the radio tower at that point.
Work is also proceeding with the seeding of the southern project areas. The seeding sub-contractor was back in town last week and some this week to reseed the berms at the golf course and the areas around the ponds with blue grass.
Seeding contractor is tilling up the berms on the golf course for reseeding |
With the reseeding on the berms at the golf course the best results are going to come from the least amount of traffic on the berms. Thus the City is asking golf patrons to refrain from driving golf carts and walking over and on the berms.
Sunday, August 18, 2013
Expansion BLVD at 4th Street To Close Monday
The contractor continues to move along and Expansion Blvd. at the intersection of East 4th Street and Expansion will close on Monday morning. The closure is anticipated to last for about a week and a half at this time.
Traffic will still be able to travel East on East 4th Street and then North onto Expansion so that access to the Rose, Tulip and Violet Lane areas is still available.
The first line of work will be field verification of a water line that feeds the Rose, Tulip, and Violet Lane areas. If the line needs to be moved water to the sub-division will be disconnected for a few hours. Please check back to this blog for further updates.
Traffic will still be able to travel East on East 4th Street and then North onto Expansion so that access to the Rose, Tulip and Violet Lane areas is still available.
The first line of work will be field verification of a water line that feeds the Rose, Tulip, and Violet Lane areas. If the line needs to be moved water to the sub-division will be disconnected for a few hours. Please check back to this blog for further updates.
Wednesday, August 14, 2013
Pipe Work Continues Forward
With two crews onsite for the contractor, Lundell Construction, the work on the East Central Storm Water Project is moving forward in good time.
The crew working in the middle area of the project along Expansion Blvd. has the pipe installed across Expansion Blvd. which should be getting paved in the next few days.
The second pipe crew is up on East 4th Street moving west installing pipe. They have East 4th Street between Expansion Blvd. and Ray Street closed during the working day but they are reopening the street to local traffic only at night.
Lundell's commitment to the project extends throughout the company as witness last week with one of the owners, Mark Lundell working on the East 4th Street Project site.
We really do have a great contractor on this project. They have been doing everything possible to make the project run smoothly and despite a very wet spring remain diligent to the schedule. They have also been diligent in protecting our environment through this process utilizing resources such as silt fence and waddles and rock checks throughout the project. We certainly appreciate all of their staff's efforts and dedication to a quality project.
Work will continue this week along both fronts and the East 4th Street crew should be getting closer to taking out the section of Expansion Blvd. at the intersection of East 4th and Expansion. For more information on street closures and detours related to this section of the work you can view of street closure map here or on our project web page.
The City, project engineer, and contractor met recently to discuss the upcoming work to be done in the cul-de-sacs of Tulip and Rose Lanes. More information on how that work will effect traffic and residential access in the area will be forthcoming in the new few days. Please check back here for more information on these impacts if you live on these two streets.
Pipe lined up ready for placement and installation. |
Pipe installed under Expansion Blvd. |
The second pipe crew is up on East 4th Street moving west installing pipe. They have East 4th Street between Expansion Blvd. and Ray Street closed during the working day but they are reopening the street to local traffic only at night.
Lundell's commitment to the project extends throughout the company as witness last week with one of the owners, Mark Lundell working on the East 4th Street Project site.
Mark Lundell compacting soils following pipe installation. |
Work will continue this week along both fronts and the East 4th Street crew should be getting closer to taking out the section of Expansion Blvd. at the intersection of East 4th and Expansion. For more information on street closures and detours related to this section of the work you can view of street closure map here or on our project web page.
The City, project engineer, and contractor met recently to discuss the upcoming work to be done in the cul-de-sacs of Tulip and Rose Lanes. More information on how that work will effect traffic and residential access in the area will be forthcoming in the new few days. Please check back here for more information on these impacts if you live on these two streets.
Seeding to Resume @ Sunrise Pointe Golf Course
Following a meeting yesterday with the seed sub-contractor and the contractor seeding activities are set to resume on the completed portions of the project (those south of the railroad tracks). This includes the Sunrise Point Golf Course where work will begin today, Wednesday, August 14, 2013. The contractor will be onsite at the golf course today removing silt fence to allow for the final fine grading to take place prior to the reseeding of the area.
The seeding contractor will be mobilizing and coming to Storm Lake today with his equipment and then starting work on Thursday. The first order of business will be the reseeding of the two large berms on the north and south of Hole #9. Once the berms are reseeded they will be mulched with straw and stakes and rope will be placed as a barrier to keep golf carts and foot traffic off the berms until grass has been established.
We are asking golfers for their help in getting the best turf we can by staying off of the berms until we have removed the ropes from the area. During the next week to 15 days we ask golfers to also be alert for small construction equipment and crews planting in the area.
Once the seeding crews have planted and mulched the berms they will start with planting of the plugs around the lower portions of the ponds. The contractor is draining the ponds currently to provide for these plantings to be done.
You may remember that the timing of the completion of the golf course work was delayed due to a very wet spring and while the contractor made every effort possible to finish the work so that seeding could be done during the allowable seed times it just didn't work out. Grass especially blue grass, the desired variety on the course, just will not grow in June and July in Iowa. The next opening for planting season is mid August and we are fortunate to be able to get the contractor in so early in the season.
The seeding contractor will also be seeding the area around the ponds by the condos and the grass waterway between the golf course and the far southern ponds. They will then move north and reseed the areas that were constructed north of East Lakeshore Drive/HWY 7.
The seeding contractor will be mobilizing and coming to Storm Lake today with his equipment and then starting work on Thursday. The first order of business will be the reseeding of the two large berms on the north and south of Hole #9. Once the berms are reseeded they will be mulched with straw and stakes and rope will be placed as a barrier to keep golf carts and foot traffic off the berms until grass has been established.
We are asking golfers for their help in getting the best turf we can by staying off of the berms until we have removed the ropes from the area. During the next week to 15 days we ask golfers to also be alert for small construction equipment and crews planting in the area.
Once the seeding crews have planted and mulched the berms they will start with planting of the plugs around the lower portions of the ponds. The contractor is draining the ponds currently to provide for these plantings to be done.
You may remember that the timing of the completion of the golf course work was delayed due to a very wet spring and while the contractor made every effort possible to finish the work so that seeding could be done during the allowable seed times it just didn't work out. Grass especially blue grass, the desired variety on the course, just will not grow in June and July in Iowa. The next opening for planting season is mid August and we are fortunate to be able to get the contractor in so early in the season.
The seeding contractor will also be seeding the area around the ponds by the condos and the grass waterway between the golf course and the far southern ponds. They will then move north and reseed the areas that were constructed north of East Lakeshore Drive/HWY 7.
Tuesday, August 6, 2013
East 4th Street Schedule Update
The Contractor anticipates that the second crew which will be working on the East 4th Street portion of the pipe work will be onsite beginning on Wednesday (August 7) to begin work. Residents and businesses using that route should be aware again of the street closures in that area. A copy of the closure map and detours is available on the project web page - see the quick links on the right hand side of the page.
PLEASE USE CAUTION WHEN TRAVELING IN THE CONSTRUCTION AREA, REDUCE SPEEDS, AND BE ALERT FOR CONSTRUCTION EQUIPMENT AND STAFF. AVOID THE AREA IF AT ALL POSSIBLE.
There is a good chance of rain today and if we were to get a good amount of rain the weather could delay the potential start of this work but at this time we anticipate crews to begin work on East 4th Street Wednesday, August 7th, 2013.
PLEASE USE CAUTION WHEN TRAVELING IN THE CONSTRUCTION AREA, REDUCE SPEEDS, AND BE ALERT FOR CONSTRUCTION EQUIPMENT AND STAFF. AVOID THE AREA IF AT ALL POSSIBLE.
There is a good chance of rain today and if we were to get a good amount of rain the weather could delay the potential start of this work but at this time we anticipate crews to begin work on East 4th Street Wednesday, August 7th, 2013.
Monday, August 5, 2013
Quick Update August 5, 2013
Things are starting to get moving with hopefully more movement starting in the next few days. Crews are onsite moving pipe toward Expansion BLVD. today with hopes of being at Expansion within the next week, weather depending.
A second pipe crew is still expected to begin work on East 4th Street yet this week put as is always possible with construction that timeline may change. The latest map showing road closures for the East 4th Street work is located on the Quick Links on the project web page.
City staff, the project engineer, and the contractor met last week to discuss traffic flow and emergency vehicle access during the work on Tulip and Rose Lanes. The contract will require that the two cul-de-sacs at the east side of those two streets will be completely removed and replaced. The replacement will cause the streets to be closed for 12-15 days for each pour which will cause access issues. We will be updating the block with additional maps in the upcoming week or so with traffic routing maps for these two areas. Work on Tulip and Rose Lanes will not occur in the next week or two and we will have maps available for the residents prior to the work beginning.
Crews work on pipe installation. |
A second pipe crew is still expected to begin work on East 4th Street yet this week put as is always possible with construction that timeline may change. The latest map showing road closures for the East 4th Street work is located on the Quick Links on the project web page.
City staff, the project engineer, and the contractor met last week to discuss traffic flow and emergency vehicle access during the work on Tulip and Rose Lanes. The contract will require that the two cul-de-sacs at the east side of those two streets will be completely removed and replaced. The replacement will cause the streets to be closed for 12-15 days for each pour which will cause access issues. We will be updating the block with additional maps in the upcoming week or so with traffic routing maps for these two areas. Work on Tulip and Rose Lanes will not occur in the next week or two and we will have maps available for the residents prior to the work beginning.