Wednesday, September 18, 2013

Pipe Work Wrapping Up

Work is moving quickly on the project at this point and the majority of the pipe work is almost complete.  The contractor was finishing up the pipe work on Tulip Lane yesterday (Tuesday, September 17).

Work on the installation of storm water pipe on Tulip Lane.
With the pipe work almost complete the remaining work is related to getting the cul-de-sacs back, finishing the dirt work and rain gardens, and seeding.  The seed sub-contractor should be on site tomorrow (Thursday) and working on the plantings in the ponds at the Golf Course and then moving up the project scope seeding the other areas that are finished.

Work on the paving back of the cul-de-sacs should be starting this week.  The main contractor will remove sections and then a sub-contractor will come in a pave the sections.  The goal of the staging is to provide access to the residential areas throughout the project.  The City urges residents and others traveling in the area to take extra pre-cautions and to ensure that they are alert to construction equipment.  This phase will take some time to complete due to the phasing but it is the only way to accomplish the repaving while still providing access.

A complete paving schedule for each cul-de-sac is available on the project web page.